Latest Rebuilding Update - 03.08.17

STRUCTURAL STEEL INSTALLATION BEGINS

You may have noticed that a crane has arrived on the site in the club carpark, which will assist with the installation of the structural steel rafters and purlins.

Over the next week, there will be more action on site including; bolting of the purlins to the rafters as well as the completion of the facades to the western and the upper northern side of the building.

The Section 96 (S96) is now in its final stages of approval with council and should be finalised next week.

Once the S96 and the Construction Certificate (CC) are obtained, it will allow for an un-interrupted continuation of the rebuilding process.